Understanding the FAR: A Beginner’s Guide to Government Contracting (Part 16)

Part 16 of THE FAR

View Previous FAR Breakdowns

Welcome back to our deep dive into the Federal Acquisition Regulation (FAR). In our previous post, we explored Contracting by Negotiation and how that method allows for flexibility in evaluating technical expertise, past performance, and price. Now, let’s move on to Part 16 of the FAR, which covers Types of Contracts. Understanding the different contract types is crucial for both government agencies and contractors, as each type comes with its own structure, risk distribution, and payment terms.

Part 16 of the FAR provides a framework for selecting the appropriate contract type based on the specifics of the procurement. The choice of contract type is one of the most important decisions in the acquisition process, as it determines how risks and rewards are shared between the government and the contractor. Different contracts are suitable for different circumstances, depending on factors such as uncertainty, scope definition, and contractor performance incentives.

Subpart 16.1 – Selecting Contract Types

Policy: The government selects contract types based on the nature of the work, the degree of uncertainty in the project, and the risk allocation between the government and the contractor. There’s no “one-size-fits-all” approach to contracting, so the government must carefully consider these factors when selecting a contract type.

Factors Affecting Contract Selection:

  • Price competition
  • Cost and technical risks
  • Market conditions
  • Urgency of need
  • Contractor’s financial stability
  • Performance incentives
Subpart 16.2 – Fixed-Price Contracts

Fixed-Price Contracts: These are the most common type of government contracts and are used when the scope of work is well-defined. In fixed-price contracts, the contractor agrees to deliver a specific product or service at a predetermined price, regardless of the actual costs incurred. The risk lies primarily with the contractor, as they must control costs to ensure profitability.

Types of Fixed-Price Contracts:

  • Firm-Fixed-Price (FFP): The price is not subject to any adjustment based on the contractor’s cost experience during performance. This contract type provides the maximum incentive for the contractor to control costs.
  • Fixed-Price with Economic Price Adjustment (FP-EPA): This contract type provides for adjustments to the contract price based on changes in economic conditions, such as inflation or fluctuations in commodity prices.
  • Fixed-Price Incentive (FPI): This contract includes incentives for cost savings or performance improvements. The contractor shares in any cost savings achieved below a target cost.
Schedule a Complimentary Consultation Today
Subpart 16.3 – Cost-Reimbursement Contracts

Cost-Reimbursement Contracts: These are used when uncertainties in the scope of work or technical requirements make it difficult to estimate costs accurately. In this contract type, the government agrees to reimburse the contractor for allowable costs incurred during the performance of the work. The contractor, however, is not guaranteed a profit but is usually paid a fee (profit), which can be fixed or variable based on performance.

Types of Cost-Reimbursement Contracts:

  • Cost-Plus-Fixed-Fee (CPFF): The contractor is reimbursed for all allowable costs and paid a fixed fee, which is determined at the time of contract award and does not change based on actual costs.
  • Cost-Plus-Incentive-Fee (CPIF): The contractor is reimbursed for allowable costs and paid an incentive fee based on how well they manage the project. If costs are below target, the contractor receives a higher fee.
  • Cost-Plus-Award-Fee (CPAF): The contractor is reimbursed for allowable costs and paid an award fee based on the government’s subjective evaluation of the contractor’s performance, typically in areas like quality, schedule, and technical achievement.
Subpart 16.4 – Incentive Contracts

Incentive Contracts: These are used when the government wants to motivate contractors to control costs, improve performance, or meet critical deadlines. The government and the contractor agree on a target cost, and the contractor’s profit depends on how well they manage the project in relation to that target.

Types of Incentive Contracts:

  • Fixed-Price Incentive (FPI): As mentioned earlier, the contractor shares in the savings or cost overruns relative to the target cost, with a ceiling price that limits the government’s liability.
  • Cost-Plus-Incentive-Fee (CPIF): The contractor earns an incentive fee based on how well they control costs relative to a target cost. If costs exceed the target, the fee is reduced, and vice versa.
Subpart 16.5 – Indefinite-Delivery Contracts

Indefinite-Delivery Contracts (IDCs): These contracts provide for the delivery of supplies or services over a specified period of time. The specific quantity of goods or services isn’t known at the time of award, but the government places orders as needed during the contract period.

Types of Indefinite-Delivery Contracts:

  • Definite-Quantity Contract: The government agrees to purchase a fixed quantity of supplies or services but schedules deliveries as needed during the contract term.
  • Indefinite-Quantity Contract (IDIQ): The government agrees to buy an indefinite quantity of supplies or services, with minimum and maximum order limits specified. Orders are placed as requirements arise.
  • Requirements Contract: The government agrees to buy all of its requirements for a particular product or service from one contractor during the contract period.
Subpart 16.6 – Time-and-Materials, Labor-Hour, and Letter Contracts

Time-and-Materials Contracts (T&M): Used when it’s difficult to estimate the extent or duration of the work required. The contractor is paid based on the number of labor hours worked at specified hourly rates and for materials at cost. This contract type places the most risk on the government, as there’s no direct incentive for the contractor to control time or costs.

Labor-Hour Contracts: Similar to T&M contracts, but the contractor provides only labor hours, and no materials are involved. The government is responsible for providing the materials.

Letter Contracts: This type of contract is used when the government needs to start work immediately and doesn’t have time to negotiate the full terms of a final contract. A letter contract authorizes the contractor to begin work while negotiations continue. Once the terms are finalized, the letter contract is converted into a formal contract.

Subpart 16.7 – Agreements

Basic Agreements and Basic Ordering Agreements (BOAs): These agreements establish terms and conditions that apply to future contracts or orders. They’re not actual contracts themselves, but they simplify the negotiation process when the government repeatedly purchases the same products or services from a contractor.

Here are some key principles and best practices to keep in mind when selecting or managing contract types:

  1. Assess Risk Allocation: Consider the level of risk each party is willing to assume. Fixed-price contracts place more risk on the contractor, while cost-reimbursement contracts shift more risk to the government.
  2. Match the Contract Type to the Work: Use fixed-price contracts when the scope is well-defined and cost-reimbursement contracts when there are uncertainties about the project’s requirements.
  3. Incentivize Performance: Use incentive contracts when you want to motivate contractors to control costs, meet performance targets, or deliver ahead of schedule.
  4. Use Indefinite-Delivery Contracts for Ongoing Needs: IDIQs and other indefinite-delivery contracts provide flexibility for repeated purchases, allowing agencies to place orders as needs arise without having to renegotiate a new contract each time.

Let’s explore some hypothetical scenarios to illustrate how these principles apply in real-world situations:

Scenario 1: Using a Firm-Fixed-Price (FFP) Contract for Construction

Your agency is procuring a contractor to build a new government office. Here’s how you ensure compliance with Part 16:

  • Firm-Fixed-Price: Since the construction project is clearly defined with detailed architectural plans and specifications, an FFP contract is used to transfer risk to the contractor and provide price certainty for the government.
  • Risk Transfer: The contractor assumes the risk of cost overruns, and the government knows the project will be completed for a fixed amount.
Scenario 2: Using a Cost-Plus-Incentive-Fee (CPIF) Contract for Research and Development

Your agency is funding a research and development (R&D) project for a new military technology. Here’s how you navigate Part 16:

  • CPIF Contract: Due to the uncertainties in the R&D process, a CPIF contract is used. This allows the contractor to be reimbursed for costs while earning an incentive fee for managing costs efficiently.
  • Risk Sharing: The government bears more risk in terms of reimbursing costs, but the contractor is incentivized to control costs and achieve milestones.
Scenario 3: Using an Indefinite-Delivery, Indefinite-Quantity (IDIQ) Contract for IT Services

Your agency requires ongoing IT support services over the next five years. Here’s how you ensure compliance with Part 16:

  • IDIQ Contract: You establish an IDIQ contract, allowing the government to order IT support services on an as-needed basis without committing to a fixed quantity of services upfront.
  • Flexibility: This type of contract provides the government with flexibility to adjust the level of services over time, depending on its evolving needs.

Here are some practical tips to help your business navigate Part 16 of the FAR:

  1. Understand the Scope and Complexity of Work: Choose the contract type that best aligns with the nature of the work, the level of uncertainty, and the risks involved.
  2. Negotiate Terms Carefully: When working with incentive contracts or cost-reimbursement contracts, ensure that the performance targets and cost ceilings are clearly defined to avoid disputes.
  3. Use Flexibility to Your Advantage: If you anticipate ongoing needs, consider using indefinite-delivery contracts to streamline future orders and reduce administrative burden.

Part 16 of the FAR covers the wide range of contract types that the government can use to procure goods and services. Whether it’s a straightforward fixed-price contract or a more complex cost-reimbursement contract, selecting the right type is crucial for managing risks, incentivizing performance, and ensuring project success.

In our next installment, we’ll explore Part 17 of the FAR, which covers Special Contracting Methods. Stay tuned as we continue to break down the FAR into manageable, understandable sections to help you succeed in government contracting.

About Us:

FedBiz Access is the leading government contracting business development and marketing firm that offers research and engagement strategy coachingregistrationscertifications, and GSA Schedules, as well as marketing packages to target government buyers. We have over 23 years of experience working with thousands of small and medium sized businesses worldwide, helping them win over $35.8 billion in awards. From registration to award, FedBiz helps you succeed in the government marketplace. 🦅